This Coast Guard circular is guidance on reducing the bow height penalty for vessels that cannot meet the minimum bow height requirements. It lets owners ask a recognized load line assigning authority to accept a bow configuration with an equivalent righting moment. It cancels NVIC 15-82.

Applies toThe action paragraph applies to the owner or owner's agent of a vessel which cannot meet the minimum bow height requirements of 46 CFR 42.20-70.

What it says

  1. This guidance provides an equivalent standard to the minimum bow height requirements in the load line regulations at 46 CFR 42.20-70.

    “This NVIC will provide an equivalent standard to the minimum bow height requirements in the load line regulations”
  2. NVIC 15-82 is canceled.

    “NVIC 15-82 is canceled.”
  3. Vessels that do not meet the minimum bow height requirements are given a bow height penalty.

    “Vessels which do not meet the minimum bow height requirements are given a bow height penalty”
  4. The owner or owner's agent of a vessel that cannot meet the minimum bow height requirements of 46 CFR 42.20-70 may request special consideration from a recognized load line assigning and issuing authority to meet the reduced penalty.

    NVIC 10-86 a.“may request special consideration from a recognized load line assigning and issuing authority to allow the vessel to meet the reduced penalty”
  5. The owner or owner's agent must prove to the assigning authority that the vessel's bow configuration yields a righting moment equivalent to that of the standard bow geometry.

    NVIC 10-86 a.“must prove to the assigning authority that the vessel has a bow configuration which yields a righting moment equivalent to that”
  6. The request should include calculations based on the principles in Enclosure (1) and, if not already submitted for the preliminary freeboard calculations, a lines plan and general arrangement plan.

    NVIC 10-86 b.“The request for penalty reduction should include the calculations based upon the principles in Enclosure (1)”
  7. The load line assigning and issuing authority will advise the vessel owner or owner's agent of the results of the review.

    NVIC 10-86 c.“The load line assigning and issuing authority will advise the vessel owner or owner's agent of the results of the review.”

Common questions

Who can review bow height equivalency calculations?

Recognized classification societies may review bow height equivalency calculations. The circular delegates review for all vessel types to the societies recognized by the Coast Guard for assigning load lines.

“This NVIC reflects current Coast Guard policy and allows recognized classification societies to review bow height equivalency calculations.”

What must an owner show to get a reduced bow height penalty?

The owner or owner's agent must prove that the vessel has a bow configuration that yields a righting moment equivalent to that of the standard bow geometry.

“must prove to the assigning authority that the vessel has a bow configuration which yields a righting moment equivalent to that”

Which directive does NVIC 10-86 cancel?

NVIC 10-86 cancels NVIC 15-82.

“NVIC 15-82 is canceled.”

Who oversees the bow height penalty reduction process?

The Commandant (G-MTH-5) will provide oversight as discussed in NVIC 10-85.

“The Commandant (G-MTH-5) will provide oversight as discussed in NVIC 10-85”

The text of NVIC 10-86

U.S. Coast Guard, NVIC 10-86 (main body; enclosures not shown)

Equivalence to Minimum Bow Height Requirements for Load Line Assignment

U.S. Coast Guard (G-MTH-5) Washington, D.C. 20593 Phone: (202) 267-2899 NVIC 10-86 5 Aug 1986 NAVIGATION AND VESSEL INSPECTION CIRCULAR NO. 10-86 Electronic Version for Distribution Via the World Wide Web Subj: Equivalence to Minimum Bow Height Requirements for Load Line Assignment

Equivalence to Minimum Bow Height Requirements for Load Line Assignment — PURPOSE. The purpose of this Navigation and Vessel Inspection Circular (NVIC) is to

clarify bow height penalty reduction calculations and procedures and to delegate the review of the calculations for all vessel types to all classification societies recognized by the Coast Guard for the purpose of assigning load lines. This NVIC will provide an equivalent standard to the minimum bow height requirements in the load line regulations (46 CFR 42.20-70 (Regulation 39 of the International Convention on Load Lines, 1966 (ICLL66))). Provision for such an equivalency is cited as "special consideration" in 46 CPR 42.20-70(c). Regulations 46 CFR 42.07-35 and 42.07.40 permit recognized classification societies to review load line calculations on behalf of the Commandant (G-MTH-5). This NVIC reflects current Coast Guard policy and allows recognized classification societies to review bow height equivalency calculations.

Equivalence to Minimum Bow Height Requirements for Load Line Assignment — DIRECTIVE AFFECTED. NVIC 15-82 is canceled.

DIRECTIVE AFFECTED. NVIC 15-82 is canceled.

Equivalence to Minimum Bow Height Requirements for Load Line Assignment — BACKGROUND. Minimum freeboard requirements were originally based upon having a certain

percentage of hull volume above the load line to provide sufficient intact reserve buoyancy to make the vessel seaworthy in heavy weather. Calculation of hull volume at that time was difficult to perform due to lack of electronic calculating aids. Therefore, when an international agreement concerning freeboards was achieved at the International Convention on Load Lines, 1930, certain assumptions were made which provided for freeboard determination based upon linear deviation from the geometry of a standard vessel. The same freeboard derivation methods were used again in ICLL66. A tabular freeboard is obtained from tables based on the length of the vessel. Corrections (both additive and subtractive) are then made to the tabular freeboard for various vessel particulars such as height and length of superstructure, block coefficient, length-to-depth ratio, and the sheer of the vessel. This corrected tabular freeboard is known as the geometric freeboard (Figure 1). The minimum bow height requirement is to ensure that a vessel’s bow configuration develops sufficient longitudinal righting energy (or trim resisting moment) to recover from a bow immersion in a seaway. It was introduced at ICLL66 after the previous requirement for forecastles on tankers was eliminated. However, the minimum bow height requirement was developed without considering the actual amount of resisting moment provided by a standardized bow configuration. Some current vessel designs are quite different from those conventional vessels used to develop the international load line requirements. A new vessel could be deficient in bow height according to the present regulations, but might have a bow configuration which develops a righting moment equivalent to that which would be developed by the standard bow geometry.

Equivalence to Minimum Bow Height Requirements for Load Line Assignment — DISCUSSION. Vessels which do not meet the minimum bow height requirements are given a bow

height penalty (Figure 1). Enclosure (1) discusses requirements for calculating a reduced bow height penalty. The calculations are based upon providing an equivalent bow volume to that of a standard vessel so that sufficient longitudinal righting energy is developed. Enclosure (2) provides a sample calculation to illustrate the method.

Equivalence to Minimum Bow Height Requirements for Load Line Assignment — ACTION.

a. The owner or owner's agent of a vessel which cannot meet the minimum bow height requirements of 46 CFR 42.20-70 may request special consideration from a recognized load line assigning and issuing authority to allow the vessel to meet the reduced penalty discussed in this NVIC. The owner or owner’s agent must prove to the assigning authority that the vessel has a bow configuration which yields a righting moment equivalent to that developed by the standard bow geometry. b. The request for penalty reduction should include the calculations based upon the principles in Enclosure (1) and, if not already submitted for the preliminary freeboard calculations, a lines plan and general arrangement plan. c. The load line assigning and issuing authority will advise the vessel owner or owner's agent of the results of the review. d. The Commandant (G-MTH-5) will provide oversight as discussed in NVIC 10-85 End: (1) Bow Height Penalty Reduction Calculations (2) Sample Calculation Non-standard Distribution: C:e Baltimore (45); Alameda (40); Port Arthur, Honolulu, Puget Sound (35); Miami, Mobile, Long Beach (25); Norfolk, Jacksonville, Portland OR (20); Boston, Portland ME, Charleston, Anchorage, Galveston (15); Cleveland (12); Cincinnati, Louisville, Memphis, Nashville, Paducah, Pittsburgh, St. Louis, Savannah, San Juan, Tampa, Buffalo, Chicago, Detroit, Duluth, Milwaukee, San Diego, Juneau, Valdez (10); Providence, Huntington, Wilmington, Corpus Christi, Toledo (5). C:m New Orleans (140); New York (70); Philadelphia (35); Houston (25); St. Ignace (5); Sturgeon Bay (4). D:l CG Liaison Officer MILSEALIFTCOMD M-65 STRAT MOB, CG Liaison Officer JUSMAGPHIL (1).

Sections it refers to

The plain-English explanation on this page was written with AI from the regulation text above and checked automatically before publishing: every quote appears in the text, every number comes from it, and a second model confirmed each statement adds nothing the text doesn't say. The regulation text governs. RegKnot is not affiliated with the U.S. Coast Guard.