33 CFR 155.1070: Vessel response plan review, revision and appeal
Last reviewed: October 14, 2026
This section sets the procedures for keeping a vessel response plan current. The owner or operator must review the plan annually and submit certain revisions for Coast Guard approval. It also covers deficiency notices, petitions for reconsideration and appeals.
Applies toVessel owners and operators with a vessel response plan; paragraph (b) applies to those subject to subparts D, E, F, G, or J of this part.
What it says
The owner or operator must review the vessel response plan every year.
33 CFR 155.1070(a)“A vessel response plan must be reviewed annually by the owner or operator.”
The annual review must take place within 1 month of the anniversary date of Coast Guard approval.
33 CFR 155.1070(a)(1)“This review must occur within 1 month of the anniversary date of Coast Guard approval of the plan.”
Owners and operators subject to subparts D, E, F, G, or J must resubmit the entire plan for approval six months before the approval period ends. Section 155.1065(c) or § 155.5065(c) identifies that period.
33 CFR 155.1070(b)“must resubmit the entire plan to the Coast Guard for approval— (1) Six months before the end of the Coast Guard approval period identified in § 155.1065(c) or § 155.5065(c);”
Revisions or amendments must be submitted 30 days before operation, with the certification required in § 155.1065(b) or § 155.5065(b).
33 CFR 155.1070(d)“Thirty days in advance of operation, the vessel owner or operator must submit any revision or amendments identified in paragraph (c) of this section.”
The Coast Guard may require a plan revision at any time. Deficiencies must be corrected within the time in the written notice, or the plan will be declared invalid.
33 CFR 155.1070(e)“Deficiencies must be corrected and submitted for acceptance within the time period specified in the written notice provided by the Coast Guard or the plan will be declared invalid”
An owner or operator who disagrees with a deficiency determination may petition for reconsideration within the compliance period or within 7 days of receiving the notice, whichever is less.
33 CFR 155.1070(f)“within the time period required for compliance or within 7 days from the date of receipt of the Coast Guard notice of a deficiency determination, whichever is less.”
The owner or operator may appeal a not-approved determination in writing within 21 days of notification.
33 CFR 155.1070(g)“Within 21 days of notification that a plan is not approved, the vessel owner or operator may appeal that determination to the Director of Incident Management and Preparedness Policy (CG-5RI).”
Changes to personnel and telephone number lists do not need prior Coast Guard approval, except as required in paragraph (c).
33 CFR 155.1070(h)“Except as required in paragraph (c) of this section, amendments to personnel and telephone number lists included in the response plan do not require prior Coast Guard approval.”
Common questions
How often must a vessel response plan be reviewed?
The owner or operator must review the plan annually. The review must occur within 1 month of the anniversary date of Coast Guard approval.
“A vessel response plan must be reviewed annually by the owner or operator.”
How long do I have to appeal a plan that is not approved?
The owner or operator may appeal in writing within 21 days of notification that the plan is not approved.
“Within 21 days of notification that a plan is not approved, the vessel owner or operator may appeal that determination to the Director of Incident Management and Preparedness Policy (CG-5RI).”
Does a change in the qualified individual require plan approval?
Yes. A change in the qualified individual is one of the changes for which revisions or amendments must be submitted for approval.
“(7) A change in the qualified individual;”
Do phone number changes need Coast Guard approval?
No prior approval is needed for amendments to personnel and telephone number lists, except as required in paragraph (c). The Coast Guard and other plan holders must be advised and given a copy as changes occur.
“The Coast Guard and all other holders of the response plan shall be advised of any revisions to personnel and telephone numbers and provided a copy of these revisions as they occur.”
The text of 33 CFR 155.1070
Electronic Code of Federal Regulations (eCFR), current as of April 16, 2026 · Read it on eCFR
Procedures for plan review, revision, amendment, and appeal
(a) A vessel response plan must be reviewed annually by the owner or operator.
(1) This review must occur within 1 month of the anniversary date of Coast Guard approval of the plan.
(2) The owner or operator shall submit any plan amendments to the Coast Guard for information or approval. Revisions to a plan must include a cover page that provides a summary of the changes being made and the pages being affected. Revised pages must further include the number of the revision and date of that revision. Although plans should be submitted electronically, for plans submitted in paper format, CG Form “Application for Approval/Revision of Vessel Pollution Response Plans” (CG-6083) located at: http://www.uscg.mil/forms/CG/CG_6083.pdf should be used in lieu of a cover letter to request the required resubmission, plan amendment, or revision.
(3) Any required changes must be entered in the plan and noted on the record of changes page. The completion of the annual review must also be noted on the record of changes page.
(b) The vessel owner or operator subject to subparts D, E, F, G, or J of this part must resubmit the entire plan to the Coast Guard for approval—
(1) Six months before the end of the Coast Guard approval period identified in § 155.1065(c) or § 155.5065(c); and
(2) Whenever there is a change in the vessel owner or operator, if the previous vessel owner or operator provided the certifying statement required by § 155.1065(b) or § 155.5065(b), then the new vessel owner or operator must submit a new statement certifying that the plan continues to meet the applicable requirements of subparts D, E, F, G, or J of this part.
(c) Revisions or amendments to an approved response plan must be submitted for approval by the vessel's owner or operator whenever there is—
(1) A change in the vessel owner or operator, if that vessel owner or operator is not the one who provided the certifying statement required by § 155.1065(b) or § 155.5065(b);
(2) A change in the vessel's operating area that includes ports or geographic area(s) not covered by the previously approved plan. A vessel may operate in an area not covered in a previously approved plan upon receipt of written acknowledgment by the Coast Guard that a new geographic-specific appendix has been submitted for approval by the vessel's owner or operator and the certification required in § 155.1025(c)(2) or § 155.5023(b) has been provided;
(3) A significant change in the vessel's configuration that affects the information included in the response plan;
(4) A change in the type of oil carried onboard (oil group) that affects the required response resources, except as authorized by the COTP for purposes of assisting in an oil spill response activity;
(5) A change in the identification of the oil spill removal organization(s) or other response-related resource required by § 155.1050, § 155.1052, § 155.1230, § 155.2230, § 155.5050, or § 155.5052 as appropriate, except an oil spill removal organization required by § 155.1050(d) or § 155.5050(d) that may be changed on a case-by-case basis for an oil spill removal organization previously classified by the Coast Guard, which has been ensured to be available by contract or other approved means;
(6) A significant change in the vessel's emergency response procedures;
(7) A change in the qualified individual;
(8) The addition of a vessel to the plan. This change must include the vessel-specific appendix required by this subpart and the vessel owner or operator's certification required in § 155.1025(c) or § 155.5023(b); or
(9) Any other significant changes that affect the implementation of the plan.
(d) Thirty days in advance of operation, the vessel owner or operator must submit any revision or amendments identified in paragraph (c) of this section. The certification required in § 155.1065(b) or § 155.5065(b) must be submitted along with the revisions or amendments.
(e) The Coast Guard may require a vessel owner or operator to revise a response plan at any time if it is determined that the response plan does not meet the requirements of this subpart. The Coast Guard will notify the vessel owner or operator in writing of any deficiencies and any operating restrictions. Deficiencies must be corrected and submitted for acceptance within the time period specified in the written notice provided by the Coast Guard or the plan will be declared invalid and any further storage, transfer, handling, transporting or lightering of oil in areas subject to the jurisdiction of the United States will be in violation of section 311(j)(5)(E) of the Federal Water Pollution Control Act (FWPCA) (33 U.S.C. 1321(j)(5)(E)).
(f) A vessel owner or operator who disagrees with a deficiency determination may submit a petition for reconsideration to Commandant (CG-MER), Attn: Vessel Response Plans, U.S. Coast Guard Stop 7516, 2703 Martin Luther King Jr. Avenue SE., Washington, DC 20593-7516 or vrp@uscg.mil within the time period required for compliance or within 7 days from the date of receipt of the Coast Guard notice of a deficiency determination, whichever is less. After considering all relevant material presented, the Coast Guard will notify the vessel owner or operator of the final decision.
(1) Unless the vessel owner or operator petitions for reconsideration of the Coast Guard's decision, the vessel's owner or operator must correct the response plan deficiencies within the period specified in the Coast Guard's initial determination.
(2) If the vessel owner or operator petitions the Coast Guard for reconsideration, the effective date of the Coast Guard notice of deficiency determination may be delayed pending a decision by the Coast Guard. Petitions to the Coast Guard must be submitted in writing, via the Coast Guard official who issued the requirement to amend the response plan, within 5 days of receipt of the notice.
(g) Within 21 days of notification that a plan is not approved, the vessel owner or operator may appeal that determination to the Director of Incident Management and Preparedness Policy (CG-5RI). This appeal must be submitted in writing to Commandant (CG-5RI), Attn: Director of Incident Management and Preparedness Policy, U.S. Coast Guard Stop 7516, 2703 Martin Luther King Jr. Avenue SE., Washington, DC 20593-7516.
(h) Except as required in paragraph (c) of this section, amendments to personnel and telephone number lists included in the response plan do not require prior Coast Guard approval.
(i) The Coast Guard and all other holders of the response plan shall be advised of any revisions to personnel and telephone numbers and provided a copy of these revisions as they occur.
Sections it refers to
The plain-English explanation on this page was written with AI from the regulation text above and checked automatically before publishing: every quote appears in the text, every number comes from it, and a second model confirmed each statement adds nothing the text doesn't say. Regulation text current as of April 16, 2026. The regulation text governs. RegKnot is not affiliated with the U.S. Coast Guard.